Overall

Future Work

Milestones
Milestone | Deliverable | Target date | Accountable |
---|---|---|---|
Measurement of water quality and DBPs in CoK ISP (A-1) | Report on DBP Status (D1) | Jul, 2024 | PhD 1, MSc 1 |
Development of BEM using relevant data from CoK2 (B-1) | Report on ISP building energy performance (D2) | Oct, 2024 | PhD 3 |
Development of predictive DBP model framework using CFD and Fugacity-approach (A-2) | Report on framework and results from CoK1(D3) | Oct, 2024 | PhD 2, PDF |
Measurement of Water Quality and DBPs in CoR1 and CoR2 (A-1) | Report on DBP Status of CoR (D4) | Apr, 2025 | PhD 1, MSc 1 |
Human health risk assessment of DBPs in ISPs using gathered data (C-1) | Report on human health risks from DBPs (D5) | Apr, 2025 | PhD 2, 3, PDF |
Completion of BEM and development of modelling guidelines for BEM in ISP (B-1) | Report on remaining ISP building energy performances and developed guidelines (D6) | Oct, 2025 | PhD 3 |
Measurement of Water Quality and DBPs in CoB and CoK2 and installation of CoK2 monitors (A-1) | Report on DBP Status and monitoring (D7) | Jan, 2026 | PhD 1, MSc 1 |
Extension of predictive CFD-Fugacity framework for DBP prediction to other ISPs, validate with CoK2 realtime data (A-2) | Report on results and validation of CFD-Fugacity approach for four ISPs (D8) | Apr, 2026 | PhD 2, PDF |
Occupant surveys of ISPs and analysis of optimal comfort levels (B-2) | Report on the optimal operational scenarios of ISPs (D9) | Apr, 2026 | PhD 2, 3, PDF |
Developments of guidelines on energy performance of ISPs based on lifecycle assessments (C-1) | Report on proposed lifecycle guidelines for ISPs (D10) | Apr, 2026 | PhD 2, 3, PDF |
Completion of human health risk assessment from remaining ISPs (C-1) | Report on human health risks from DBPs (D11) | July, 2026 | PhD 2, 3, PDF |
Development of optimized WHEN model and optimal operation strategies (C-2) | Report on WHEN performance (optimization) model (D12) | Oct, 2026 | PhD 3, PDF |
Development of ePool dashboard (C-3) | Report on ePool dashboard performance (D13) | Apr, 2027 | PhD 3, PDF |
Compilation of project results | Final Report | Apr, 2027 |
*Target dates are tentative and subject to change